Hoàn thành lắp đặt máy biến áp 500kV 900MVA thứ hai tại Đức Hòa - Nâng cao năng lực truyền tải điện

Successful Energization of Second 500kV 900MVA Transformer at Đức Hòa Substation Marks Major Milestone in Vietnam's Power Infrastructure

In a significant achievement for Vietnam's power sector, the National Power Transmission Corporation (EVNNPT) successfully completed the energization of the second 500kV 900MVA transformer (AT1) at Đức Hòa Substation at 02:58 on July 16, 2026. This milestone accomplishment, achieved through close coordination with relevant units, marks a critical advancement in enhancing power transmission capacity for Southern Vietnam and represents a major step forward in the country's power infrastructure development.



Historic Achievement in Power Transmission

The successful energization of the second 500kV 900MVA transformer at Đức Hòa Substation concluded an intensive preparation process characterized by meticulous coordination among various stakeholders. The energization process was executed in strict accordance with rigorous technical procedures, ensuring absolute safety for both the power system and operational personnel.



This high-capacity transformer significantly enhances the power transmission capacity from Central to Southern Vietnam, addressing the region's growing electricity demand. The new transformer will alleviate the load burden on existing transmission lines while simultaneously improving the overall reliability of the power system. The project also includes the installation of a 220kV 250MVA transformer, further strengthening the substation's capabilities.



Key Technical Specifications

ParameterSpecification
Rated Capacity900 MVA
Rated Voltage500/220 kV
Frequency50 Hz
Electrical InsulationSF6-free
Cooling SystemSelf-cooled (OA)

Strategic Importance of the Project

The project to install the second 500kV 900MVA transformer and a 220kV 250MVA transformer at Đức Hòa Substation holds strategic significance for Vietnam's national power system development. This initiative addresses the critical issue of power overload in Southern Vietnam, particularly in Ho Chi Minh City and surrounding provinces.



The successful implementation of this project delivers multiple benefits:


  • Increases power transmission capacity from Central to Southern Vietnam by 900 MW
  • Improves power quality and reduces transmission losses
  • Enhances the reliability and stability of the regional power system
  • Meets the growing economic and social development needs of Southern Vietnam
  • Prepares the infrastructure for future development of new power sources in the region

Key Stakeholders and Their Contributions

The successful completion of this project resulted from close collaboration among multiple organizations:


  • National Power Transmission Corporation (EVNNPT): As the leading entity, responsible for overall project management and implementation guidance
  • NPTPMB Project Management Board: Directly managed and implemented project activities
  • National System Market Operation (NSMO): Ensured safe and stable power system operation
  • Southern System Operation Dispatch Center (SSO): Coordinated transformer energization and subsequent operational activities
  • Construction units and equipment suppliers: Ensured quality and timely project completion

Challenges and Solutions

Throughout the project implementation, stakeholders faced several significant challenges:


  • Schedule challenges: The project needed to be completed rapidly to meet increasing electricity demand. Solution: Increased manpower, machinery, and implementation of multi-shift work schedules
  • Technical challenges: Installation and operation of high-capacity transformers require specialized technical expertise. Solution: Enhanced personnel training, application of advanced technologies, and expert support from equipment suppliers
  • Safety challenges: High-voltage electrical work inherently carries significant risks. Solution: Strict adherence to safety procedures, comprehensive preventive measures, and robust contingency plans for emergency situations

Future Development Plans

The successful energization of the second 500kV 900kVA transformer at Đức Hòa Substation represents a significant advancement but is not the final goal. EVNNPT's future plans include:


  • Completion of remaining project components
  • Investment in upgrading other substations nationwide
  • Development of high-voltage transmission networks to connect new power sources
  • Implementation of digital technologies in power transmission operation and management

Conclusion

The successful energization of the second 500kV 900MVA transformer at Đức Hòa Substation stands as a remarkable achievement for Vietnam's power industry. This project not only contributes to national energy security but also establishes a foundation for sustainable economic and social development in Southern Vietnam. The seamless coordination among various units has demonstrated a spirit of unity and high determination in accomplishing this critical mission.



The National Power Transmission Corporation (EVNNPT) remains committed to continued efforts and coordination with relevant units to complete other key projects, contributing to the modernization of Vietnam's national power system and meeting the increasingly high demands of consumers and businesses.